BATUSAN is committed to personal safety and the long service life of API-6D Ball Valves with this instruction manual, Installation, Operation and Maintenance Manual. This Natural Gas Ball Valve Maintenance manual will provide all necessary safety guidelines for the valves, including information on handling, storage, installation, operation and Natural Gas Ball Valve Maintenance. Please read it carefully before installing or maintaining the valve.

BATUSAN provides general guidelines in this manual. The end user must therefore take responsibility for the correct valve selection, sizing, installation, operation and Natural Gas Ball Valve Maintenance of Batusan valve products. The end user must read this document in conjunction with the instructions supplied with the product.

Purpose

The BALL VALVE is a type of valve, manufactured according to the relevant standard, that directs, transmits or stops the flow of fluids by the movement of the ball inside its body. The purpose of this manual is to ensure that the ball valve is installed in accordance with the valve conditions, so that it can fulfil its working principles, and that it is operated in environments suitable for these conditions. For this purpose, information and instructions are given on the appropriate conditions and on the situations / issues to be considered.

The user is responsible for the problems and consequences arising from behaviors contrary to the specified issues, including those caused by neglected Natural Gas Ball Valve Maintenance.

Considerations in ball valve selection

The Natural Gas Ball Valve Maintenance instructions list the following criteria for selecting the correct valve:

  • Medium of use (the fluid passing through the valve): the valve should be selected according to whether the fluid is liquid, gas, air or a dense fluid containing solid particles, and whether it is corrosive or not.
  • Concentration and temperature of the fluid (max. and min.): the maximum and minimum operating temperatures of the fluid passing through the valve must be known.
  • Operating pressure (max. operating pressure): the maximum pressure of the fluid passing through the valve.
  • Type of connection to the circuit: threaded, flanged, socket, welded or union.
  • Size, or the amount of fluid to be passed per hour.
  • Compliance with international standards: TSE, API, DIN, EN, ANSI.
  • Valve passage type: full bore or reduced bore.

Packaging

Packaging requirements in the Natural Gas Ball Valve Maintenance instructions are as follows:

  • Batusan natural gas valves are protected against foreign objects entering the line connection points. It is recommended not to remove the packaging and covers of the valve until it is connected to the cleaned line.
  • Batusan valves are packaged, boxed and palletized in accordance with the Transportation, Storage, Packaging and Shipment procedure.

Unless the customer specifies a special request, Batusan ships the valves in a cardboard box on a pallet or in a wooden box on a pallet. To keep Natural Gas Ball Valve Maintenance costs low, it is recommended that the customer keeps the delivered valves in a closed storage area, away from water, moisture and dampness.

Storage

The Natural Gas Ball Valve Maintenance instructions define the following storage conditions:

    • Valves must never be stacked on top of each other, in order to avoid any adverse situation that could affect valve performance and cause injury to personnel.
    • The boxes should be opened and the valves inside checked to make sure that they have not been damaged during transport.
    • If the valve is removed from the box or pallet, the accessories on the valve must be protected from any crushing or impact.
    • For long-term storage (min. 6 months), the line connection covers of the valve are opened, the unpainted parts are lubricated with anti-corrosion oil and the flanges are closed again with covers.
    • During shipment or storage, the weight of the product is checked and the product is shipped with a suitable carrier.

Transport

For transport, the Natural Gas Ball Valve Maintenance instructions require the following precautions:

  • Cloth slings should be used when opening the box to prevent any damage to the valve.
  • When lifting the valves, it is recommended to use lifting devices suitable for the valve weight.
  • The transportation of ball valves larger than 25 kg is provided by the lifting lugs on the valve, which have their own lifting points designed to carry the load of the valve.
  • For valves without transportation lugs, the valve can be lifted through the stud holes in the flanges used for connection to the installation.
  • The gear box or actuator must not be used for lifting the valve.
  • For valve and occupational safety, the lifting equipment must always be double-checked before each lifting operation.
  • Never remove the valve flange protection during lifting / transportation, to prevent foreign matter from entering the valve.

Points to be considered when using ball valves

The following operating points are taken from the Natural Gas Ball Valve Maintenance instructions:

  • Batusan natural gas ball valves are cleaned and protected against foreign objects entering the line connection points. It is recommended not to remove the packaging and covers of the valve until it is connected to the line.
  • The valve should be left in the fully open or fully closed position. Owing to its working principle, a valve left in the half-open position damages the PTFE ball seals and causes the valve to leak.
  • Apply force to the valve handle only for the opening and closing positions, in the direction of the arrow. Do not apply force once the lever rests against the stop pin.

The operating conditions are indicated on the valve as the maximum working pressure in BAR.

Matters to be considered in ball valve installation

Correct installation is the starting point of trouble-free Natural Gas Ball Valve Maintenance; observe the requirements below.

For valve mounting

  • Before installing the valve, the line must be cleaned with compressed air or steam to remove any burrs, rust, foreign objects and dirt that may be present in the pipeline.
  • Line conformity check should be performed and line information and valve label information should be compared.
  • The labels / covers on both flanges of the new valve must be removed before installation.
  • If a flow direction is marked on the valve, the valve is installed so that it matches the flow direction of the line. If no flow direction is marked on the valve, it can be installed in either direction.
  • The valve to be used must be of a suitable standard, pressure class and diameter for the line to which it will be connected.
  • The axes of the pipes to be installed and the hole axes of the connection element to be used must be on the same axis. Example: If a flange is used as the connection element, the bolt hole axes must be on the same axis. (Excessive stresses on the valve caused by such axis misalignments will jeopardise the tightness.)
  • If the connection element is flange, the gaps are removed by tightening the bolts mutually, then they are tightened mutually at the given torque values.
  • If a space is left for the valve during installation, it must be calculated from the length of the valve to be used and the thickness of the sealing elements.
  • If the connection type is threaded, the thread length on the pipe must not be shorter than the thread length of the valve.
  • A leakage check must be performed by testing at 1.5 times the rated pressure indicated on the label.
  • Care should be taken to ensure that the valve to be installed in the installation is in the open position, and the handle should be in the flow direction.
  • The flange side of the valve to be installed in the installation, where the technical information is written, is mounted as input. Then the other side is mounted to the installation without giving the opportunity to create tensile stress. After installation, and after any Natural Gas Ball Valve Maintenance, the installation should be tested with 1.5 times the operating pressure and leakage control should be performed.

For the flange sealing element

Sealing elements are the most frequent item in Natural Gas Ball Valve Maintenance:

  • A sealing element suitable for the fluid type and pressure must be selected.
  • The surfaces of the sealing element to be used in flange connections must be smooth.
  • De-assembled, deformed sealing element should not be used, a new one should be installed.

During Natural Gas Ball Valve Maintenance, when installing the sealing element, care must be taken not to obstruct the valve bore. (Sealing elements: Klingerit, PTFE, O-ring, rubber of suitable hardness.)

Things to be considered when using ball valve

Day-to-day use directly affects Natural Gas Ball Valve Maintenance intervals:

  • Natural Gas Ball Valve Maintenance starts on delivery: remove the valve from its packaging only when you are ready to connect it to the installation.
  • The valve should be left in the fully open or fully closed position. Owing to its working principle, a valve left in the half-open position damages the PTFE ball seals and causes the valve to leak.
  • Apply force to the valve handle only for the opening and closing positions, in the direction of the arrow. Do not apply force once the lever rests against the stop pin.
  • The operating conditions are indicated on the valve as the maximum working pressure in BAR.
  • The operating temperature range is limited to -5 to +60 °C.
  • Valves complying with the TS 9809 and TS EN 331 standards are used as distribution and service valves in natural gas, LPG and combustible gas installations, and Natural Gas Ball Valve Maintenance follows the same standards.

Natural Gas Ball Valve Maintenance

  • There is no specific periodic Natural Gas Ball Valve Maintenance interval. A disc spring is fitted under the stem nut; it ensures permanent sealing in the labyrinth stuffing box under varying internal pressure and temperature. If the sealing performance decreases slightly after long-term use, tightness is restored for a long time by tightening the stem nut slightly.
  • Natural Gas Ball Valve Maintenance is straightforward for three-piece ball valves: since these valves are designed in three parts, the middle body part, which contains all the moving parts, can easily be removed from between the end pieces and the parts can be replaced.
  • Burak Type Ball Valves are designed in two parts, which simplifies Natural Gas Ball Valve Maintenance: the parts can be replaced by simply removing the cover on the middle body part, which contains all the moving parts.

Tools and materials to be used

Natural Gas Ball Valve Maintenance requires only a simple tool set: a double-ended wrench, suitable for connecting bolts and nuts.

Connection bolts used in flanges

The Natural Gas Ball Valve Maintenance instructions give the following connection bolt dimensions for tailed flanges. L is the bolt length and Ø d the bolt diameter, both in millimetres.

Valve size PN 16 (DIN 2633 tailed flange) — L PN 16 — Ø d PN 40 (DIN 2635 tailed flange) — L PN 40 — Ø d
DN 10 50 12 50 12
DN 15 50 12 50 12
DN 20 50 12 50 12
DN 25 50 12 50 12
DN 32 50 16 55 16
DN 40 55 16 55 16
DN 50 55 16 60 16
DN 65 55 16 65 16
DN 80 60 16 65 16
DN 100 60 16 75 20
DN 125 65 16 80 24
DN 150 70 20 85 24
DN 200 75 20 90 27

Conclusion

If the BALL VALVE, which we call the valve of our age, is to work properly, placing a strainer (filter) in the main circuits will reduce operating costs. The BALL VALVE connected to the installation should be operated in the fully open or fully closed positions, in order to prevent possible leaks and operating costs.