BATUSAN is committed to your personal safety and to the long service life of Steel Ball Valves with this Installation, Operation and Maintenance Manual. This Steel Ball Valve Maintenance manual provides all necessary safety guidelines for the valves, including information on handling, storage, installation, operation and maintenance of the valve. Please read it carefully before installing or maintaining the valve.

BATUSAN provides general guidelines in this manual. The end user must therefore take responsibility for the correct valve selection, sizing, installation, operation and Steel Ball Valve Maintenance of Batusan valve products. The end user must read this document in conjunction with the instructions supplied with the product.

Purpose

The purpose is to ensure that the BALL VALVE, a type of valve manufactured to the relevant standard that directs, transmits or stops fluids by the movement of the ball inside its body, is installed in accordance with the valve conditions so that it can fulfil its working principle, and that it is operated in environments suitable for these conditions. For this purpose, information and instructions are given on the appropriate conditions and on the situations / issues to be considered.

The user is responsible for the problems and consequences arising from behaviour contrary to the specified issues.

Considerations in ball valve selection

The Steel Ball Valve Maintenance instructions list the following criteria for selecting the correct valve:

  • Medium of use (the fluid passing through the valve): the valve should be selected according to whether the fluid is liquid, gas, air or a dense fluid containing solid particles, and whether it is corrosive or not.
  • Concentration and temperature of the fluid (max. and min.): the maximum and minimum operating temperatures of the fluid passing through the valve must be known.
  • Operating pressure (max. operating pressure): the maximum pressure of the fluid passing through the valve.
  • Type of connection to the circuit: threaded, flanged, socket, welded or union.
  • Size, or the amount of fluid to be passed per hour.
  • Compliance with international standards: TSE, API, DIN, EN.
  • Valve passage type: full bore or reduced bore.

Storage

The Steel Ball Valve Maintenance instructions define the following storage conditions:

  • Valves must never be stacked on top of each other, in order to avoid any adverse situation that could affect valve performance or cause injury to personnel.
  • The boxes should be opened and the valves inside checked, so that the user can make sure that no damage has occurred during transportation.
  • When the valve is removed from the box or pallet, the accessories on the valve must be protected from any crushing or impact.
  • For valves stored for a long period (min. 6 months), the line connection covers of the valve are opened, the unpainted surfaces are lubricated with anti-corrosion oil and the flanges are closed again with covers.
  • During shipment or storage, the weight of the product is checked and the product is shipped with a suitable carrier.

Transport

For transport, the Steel Ball Valve Maintenance instructions require the following precautions:

  • Cloth slings should be used when opening the box, to prevent any damage to the valve.
  • When lifting the valves, it is recommended to use lifting devices suitable for the valve weight.
  • Ball valves heavier than 25 kg are transported by means of the lifting lugs on the valve, which are lifting points designed to carry the load of the valve.
  • Valves over 25 kg without lifting lugs can be transported through the stud holes in the flanges that connect the valve to the installation.
  • The gearbox or actuator must not be used to lift the valve.
  • For the safety of the valve and of personnel, the lifting equipment must always be double-checked before each lifting operation.
  • Never remove the valve flange protection during lifting / transportation, to prevent foreign matter from entering the valve.

Points to be considered when using ball valves

The following operating points are taken from the Steel Ball Valve Maintenance instructions:

  • Batusan Ball Valves are cleaned, and their line connection points are protected against the entry of foreign objects. It is recommended not to remove the packaging and covers of the valve until you connect it to the line.
  • The valve should be left in the fully open or fully closed position. Due to its working principle, a valve left in the half-open position damages the PTFE ball seals and causes the valve to leak.
  • Apply force to the valve handle only to open and close the valve, in the direction of the arrow. Do not apply force once the lever rests on the stop pin.

During Steel Ball Valve Maintenance, note that the operating conditions are marked on the valve; the maximum working pressure is given in BAR.

Matters to be considered in ball valve installation

Correct installation is the starting point of trouble-free Steel Ball Valve Maintenance; observe the requirements below.

For valve mounting

  • Before installing the valve, the line must be cleaned with compressed air or steam to remove any burrs, rust, foreign objects and dirt that may be present in the pipeline.
  • A line conformity check must be performed, and the line information must be compared with the information on the valve label.
  • The labels / covers on both flanges of the new valve must be removed before installation.
  • If a flow direction is marked on the valve, the valve is installed so that this direction matches the flow direction of the line. If no flow direction is marked on the valve, it can be installed in either direction.
  • The valve must be of a suitable standard, pressure class and diameter for the line to which it will be connected.
  • The axes of the pipes to be installed and the hole axes of the connection element to be used must be on the same axis. Example: if a flange is used as the connection element, the bolt hole axes must be on the same axis. (Excessive stresses on the valve caused by such axis misalignments will jeopardise the tightness.)
  • If the connection element is a flange, the gaps are first closed by tightening the bolts crosswise; the bolts are then tightened crosswise to the specified torque values (see Table 4 and the Torque Sequence figure in the manual).
  • If a space is left for the valve during installation, it must be calculated from the length of the valve to be used and the thickness of the sealing elements.
  • If the connection type is threaded, the thread length on the pipe must not be shorter than the thread length of the valve.
  • A leakage check must be performed by testing at 1.5 times the rated pressure indicated on the label.
  • Make sure that the valve to be installed is in the open position, with the handle in line with the flow direction.
  • The valve is installed with the flange side carrying the technical information as the inlet. The other side is then connected to the installation without creating tensile stress.

For the flange sealing element

Sealing elements are the most frequent item in Steel Ball Valve Maintenance:

  • A sealing element suitable for the fluid type and pressure must be selected.
  • The surfaces of the sealing element to be used in flange connections must be smooth.
  • A sealing element that has been dismantled or deformed must not be reused; a new one must be installed.

During Steel Ball Valve Maintenance, when installing the sealing element, care must be taken not to obstruct the valve bore. (Sealing elements: Klingerit, PTFE, O-ring, rubber of suitable hardness.)

Periodic check and general Steel Ball Valve Maintenance

Inspection

To ensure the design life of the valve, a regular Steel Ball Valve Maintenance inspection program is required. Depending on the service conditions and the frequency of valve operation, the following checks should be carried out in the field, in parts and in whole, to verify that the valve is operating correctly:

  • Paint integrity
  • Dust deposits
  • Signs of rust, external corrosion and oxidation
  • Condition of vent and drain parts
  • Lubrication of screw threads and bearings
  • Internal and external leakages

Periodic check

A routine Steel Ball Valve Maintenance check must be carried out at intervals not exceeding two years from the date of delivery. Underground valves cannot be subjected to routine Steel Ball Valve Maintenance, but a preventive Steel Ball Valve Maintenance and inspection program is required once a year.

Before any Steel Ball Valve Maintenance, the valve is depressurised and the temperature is checked at the vent and drain lines. Electrical connections are disconnected and the valve is cleaned. Failure to follow any of the above procedures can result in a serious health and safety hazard to personnel.

Generally, routine Steel Ball Valve Maintenance covers stem and seat ring lubrication, gearbox operation check and end connections, body flange gasket leakage check and, if present, leakage check of relief and vent valves and drain plugs. If there are signs of nonconformity during the check, they are recorded in the report; the relevant persons are notified and troubleshooting service is requested.

Additional Steel Ball Valve Maintenance

Additional Steel Ball Valve Maintenance operations are not performed according to the schedule; this is the intervention performed when the valve is not working. Trained personnel should perform the above-mentioned intervention on the required dates with the appropriate documentation.

Replacement of gaskets

  • Isolate the line or relieve its pressure, and work with the valve in the open position.
  • Mark the body and the body flange in the same alignment on the right and left sides with permanent paint or a marker, so that these marks ensure they are reassembled in the same position. This is very important, as it guarantees sealing on the same surface. Unscrew and remove the body studs and nuts.
  • Remove the cover and mark the position of the ball in line with the marked side (do not mark the surfaces in contact with the PTFE or SWG seat). Remove the old gasket and dispose of it at the universal waste collection point.
  • Check the gasket contact surface for damage and deterioration. Clean the surfaces and remove any foreign material and/or debris. Clean the gasket seat with a rough cloth. Any leak at the seal can lead to damage. To ensure a good seal, the contact surfaces must have a surface roughness of 1.6 to 3.2 Ra.
  • Install the new gasket without using any filler material during this replacement.
  • Assemble the body flange to the body with the ball in the open position. The tightening values of the body studs / nuts or bolts shall be according to Table 4 of the manual.

Steel Ball Valve Maintenance preparation

  • Find the instructions and drawings (drawing numbers / ref. no.) of the valve to be maintained. Steel Ball Valve Maintenance must not be performed without instructions and drawings.
  • Check the safety of the Steel Ball Valve Maintenance area.
  • If there are any flammable or explosive substances, electric current, pressure, air pollutants or poisonous substances, warn the relevant persons to remove them.
  • Check that you have sufficient equipment for the disassembly and assembly torques (see Table 4).
  • Ensure that you have an adequate supply of the necessary lubricants and cleaners.
  • If there are gearboxes and actuators, have their catalogs and Steel Ball Valve Maintenance instructions available.

Steel Ball Valve Maintenance and lubrication procedure

The Steel Ball Valve Maintenance instructions specify the following lubrication steps:

  • Cleaning will be carried out after safety measures have been approved. Take precautions for cleaning waste, prevent it from being dispersed into the environment.
  • A special-purpose, high-quality Batusan seat flush cleaner is injected into the emergency sealing system. This removes old grease and other foreign materials, which would cause leakage and high torque, from the critical sealing area.
  • With the valve in the fully closed position, additional special-purpose Batusan sealing grease, selected according to the type of fluid, is slowly injected into the emergency sealing system on the high-pressure side of the valve.
  • If possible, the additional sealing grease is distributed evenly over the entire ball surface by moving the ball slightly.
  • Damaged or defective emergency sealing (injection) fittings can be replaced while the valve is under line pressure. However, it must first be ensured that the check valve in the fitting is working.
  • Waste from lubrication must be disposed of in accordance with the “Waste Management” procedure.

Control procedure

The control procedure in the Steel Ball Valve Maintenance instructions covers these steps:

  • Confirm safety precautions for control and live test.
  • If the system pressure can be measured for the test, obtain the information from its source.
  • For DBB type valves, open the drain or vent valve and start relieving the pressure from the body cavity.
  • If pressure is being released from the body cavity, measure the leakage against the API 6D leakage tolerances. Measuring bubbles with a tube is sufficient for this.
  • If the measurement exceeds the standard values, record a leak and propose a repair procedure (gearbox adjustment, seat and stem seal adjustment, seat repair lubrication, etc.).

Dismantling procedure

The Steel Ball Valve Maintenance instructions describe the dismantling sequence as follows:

  • Cleaning will be carried out after safety measures have been approved. Take precautions for cleaning waste, prevent it from being dispersed into the environment.
  • Clean, especially the areas to be accessed for Steel Ball Valve Maintenance, ensuring that they are thoroughly cleaned.
  • If there are weights and sizes that cannot be lifted and dismantled by hand, install lifting equipment.
  • Follow the recommended sequence by referring to the detailed drawings of the dismantling operation. During dismantling, always mark (with paint or pencil) and number the parts before separating them, so that their orientation is easily understood and they are refitted in the same orientation.
  • During disassembly, inspect the parts and photograph immediately any damage found, such as corrosion or deformation.
  • Record the actions to be taken to eliminate the damage and attach the photographs as evidence.
  • Remove rust and/or dirt without damaging the dismantled parts.
  • Separate the parts to be replaced and check their compatibility with the spare parts.
  • In valves that cannot provide sealing, the ball and O-rings are damaged; the valve must be removed from the line.

Reassembly and assembly

For reassembly, the Steel Ball Valve Maintenance dismantling procedure must be reversed. For assembly of the body, strictly observe the warnings on the relevant technical drawing and its annexes. When in doubt, always consult Batusan technical service or request service.

Final adjustment and checks

Final adjustments are completed as described in the Steel Ball Valve Maintenance instructions:

  • Verify that the opening and closing direction markings are correct.
  • Measure and record the opening and closing torque.
  • Check full opening and closing (this can be done together with the sealing check).
  • Confirm the safety precautions for the check and the live test.
  • If the system pressure can be measured for the test, obtain the information from its source.
  • For DBB type valves, open the drain or vent valve and start relieving the pressure from the body cavity.
  • If pressure is being released from the body cavity, measure the leakage against the API 6D leakage tolerances. Measuring bubbles with a tube is sufficient for this.

If the measurement exceeds the standard values, record a leak and propose a repair procedure (gearbox adjustment, seat and stem seal adjustment, seat repair lubrication, etc.).

Steel Ball Valve Maintenance marking

Copy the Steel Ball Valve Maintenance records made in the maintenance document to the valve file. If service has been performed, add it to the service attachment. If spare parts have been used, add the spare part entries to the valve file and to the service form attachment. Adjustment and measurement records, the opinions of the maintenance staff and suggestions for future Steel Ball Valve Maintenance are stated on the service form.

Apply the field service label and record the latest Steel Ball Valve Maintenance date. This period should not be more than 12 months.

Decommissioning and disposal

Steel Ball Valve Maintenance ends with decommissioning: at the end of its working life, the valve is removed from the line with a procedure appropriate to the valve type and installation conditions. To avoid polluting the environment while dismantling the valve, equipment must be used to prevent leakage at the valve inlet and outlet from contaminating the environment. Bring the valve to a place that complies with European, national and regional standards and store it until the date of disposal.

The valve may contain toxic, corrosive and harmful substances. It must be cleaned with high-pressure steam before dismantling. Personnel must wear protective equipment appropriate to the contamination while carrying out these operations. The waste generated during this process must be disposed of in accordance with European, national, regional and municipal directives and/or waste laws and/or hazardous material laws. The paint layer on the valve is removed by sandblasting. Residual metallic parts can be recycled in a steel mill. Plastic parts (O-rings, packing rings, etc.) must be disposed of in accordance with European, national, regional and municipal directives and/or waste laws and/or hazardous material laws.

Beyond routine Steel Ball Valve Maintenance, additional documents — mounting drawing (gear boxed) and parts list and definitions — are special order documents; refer to the order file.

Venting and draining of Batusan ball valves

Venting and draining are the most hazardous part of Steel Ball Valve Maintenance.

The valve cavities are pressurised during venting and draining. This dangerous operation should be performed by experienced personnel.

  • For operator safety, Batusan A.Ş. recommends the use of a bleed fitting for venting. The vent plug must not be removed until all pressure in the body cavities has been completely relieved.
  • For operator safety, Batusan A.Ş. recommends the use of a bleed fitting for draining. The drain plug must not be removed until all pressure in the body cavity has been completely relieved.
  • In either case, the fluid in the pipeline may be toxic, corrosive or flammable. The valve must be decontaminated according to a suitable standard before the operator works on it.
  • The operator must use protective equipment suitable for the chemical and physical effects to which he/she will be exposed.
  • If a safety valve is available to prevent the uncontrolled release of fluid at high temperature and pressure that may be harmful to human health, it is recommended that this safety equipment be connected to a suitable manifold to control the released fluid. If a bleed fitting is not available, do not use the vent and drain plugs to relieve pressure from the body cavities.
  • Tools used for work on the external surfaces of the valve (grinding, welding, cutting, etc.) must be of the non-sparking type. The use of these tools must be subject to a permit. This permit is not valid in the presence of an explosive atmosphere or flammable deposits outside or inside the valve; such deposits must be removed before starting work.

Conclusion

If you want the BALL VALVE, which we call the valve of our age, to work properly, placing a strainer (filter) in the main circuits will reduce operating costs. The BALL VALVE connected to the installation must be operated in the fully open or fully closed position in order to prevent possible leaks and operating costs.

Steel Ball Valve Maintenance Documents

Download as PDF (English / Turkish)

Steel Ball Valve Product Page

Steel ball valve

Steel Ball Valve Product Gallery

See More Product Images